What should you do if you don’t agree with the project business case?

The answer depends on what makes you uncomfortable.

The project business case forms the basis of the project. Get it wrong and the likelihood of a successful project is low.

If you believe the business case data lacks integrity, discuss this with your sponsor immediately. Contrast your information with what’s in the business case and work through the differences. The business case sets expectations, so you’ll eventually need to compare project outcomes against the business case. Don’t wait until the end of the project to challenge the business case. Take action now!

If you’re concerned with risk in the business case, seek to understand your sponsor’s risk profile. As a project manager, part of your role is to ensure your sponsor and key stakeholders understand the project risks. Your role is NOT to ensure risk goes away, When you’re concerned with business case risk, point out the risks to stakeholders and establish response plans. When you understand the risks your sponsor is comfortable and uncomfortable with, you can perform risk management effectively.

If the business case was not built collaboratively, review the business case with key stakeholders. They usually focus on their own interests and perceptions of risk and may be uncomfortable with the business case or its approaches. Discussions to analyze and align the business case with key stakeholders are critical. Moving forward with a business case that hasn’t been reviewed and agreed upon makes it difficult to get staffing and decision-making support.

Proactively addressing issues in the business case will help you deliver your project successfully as well as establish your authority with project stakeholders.

What if the sponsor doesn’t want a feasibility study – they want a 100% guarantee!!!

Projects are risky by definition! You are trying to create something that has never been created before. Some executives find this uncomfortable and request a feasibility study to determine whether the project is viable. It’s a smart thing to do: it helps you build a good initial scope statement and project charter. However, if the feasibility study is supposed to create certainty about the project outcome – meaning no risk – you’ve got a problem. Here are some tips if you find yourself in this situation.

  1. Focus on creating a risk plan and sharing it enthusiastically. This may seem a bit counter-intuitive. You have executives who don’t want risk, and the advice is to shove a risk plan in their face! The fundamental truth is that projects involve risk. Embrace that! Presenting a methodical way to approach risk is the best way to balance the reality of those risks with a sense of control.
  2.  Package your project approach as a story. When your executive sees how the project can come to pass via a believable story, you can ease their fears and allow a reasonable project to move forward.
  3.  Focus on the steps in your plans and how you can validate each step as they occur. Executives often fear that they will lose control and incur large expenses or delays. Building sound plans and project controls can ease your executives’ anxiety. Make your sponsor comfortable that they will have control over the project and can act proactively if things go sideways. Doing so will put your sponsor, yourself and your organization in a much better position to deliver a viable project.
  4. Understand your sponsor’s greatest concerns and communicate status about those concerns. If they are concerned about spending, create as detailed a budget and spending plan as you can and review status regularly. When the status isn’t good, report it quickly  — along with actions that can be taken. Ensure a sense of control and understanding is present regarding your project, and you and your sponsor are more likely to work together to produce great project outcomes.

Top 5 Project Management Skills You Never Knew You Needed

As a project manager no two days are the same. Business changes, project dynamics, and the myriad stakeholders you deal with are just the beginning. For daily entertainment, here are a few additional project management skills you must develop and deploy to be effective:

  1. Storyteller – Effective conversations and project documentation are the beginning of your project story. What you really need is vivid communication–the story of how your project can progress from idea to reality. Senior leaders need reassurance, often in the form of hero reports and processes that save the day. Practice telling the story of your project. To be certain your story will sell your senior leaders, make it part Marvel action movie and part warm snuggly lullaby. Do that, and you’ll be in your project’s driver’s seat.
  2. Non-insulting Consultant – One of the more challenging things a project manager does is turn away work. That’s right – you have to say no to some project assignments. Pet projects, impractical projects that sponsors erroneously assume employees will buy into, and other unrealistic project concepts will cross your desk for justification. When you find yourself in this position, you need to put on your consulting hat and convince your enthusiastic sponsor their idea won’t fly. You have to be firm and direct and, at the same time, avoid insulting them. Take the approach of steward of your sponsor’s business and assure them that your job is to protect them from issues that impact the bottom line. Consider telling a good project horror story (see item 1).
  3. The Battle-revealer and Peacemaker – Your project sponsor may be totally convinced about a project, while other key stakeholders think differently. Finding those not-so-on-board stakeholders and revealing the battle that needs to be fought is critical for success. Otherwise, you’ll have one significant stakeholder tell you to go north while another tells you to go south. Good luck with THAT! Find the requirement and prioritization mismatches, get the combatants in a room, and help them clearly articulate their differences. You act as the peacemaker and look for compromise, if necessary. Then your life as project manager will be much easier.
  4. The Discoverer of wobbly truth – The people you need to work on your projects are almost always working on other things, too. (If you run a project with 100% dedicated resources, you haven’t experienced the full fun of being a PM!) Your project team members are juggling things and almost always underestimate. They try to be diligent, but they’re usually optimistic about what they can produce, in quantity and quality. Gently and compassionately, you need to find the truth about what your project team can produce and the status of their work. Wobbly truth (a well-intended statement that isn’t a lie, but doesn’t turn out to be accurate) has spawned more nightmares than Dracula—at least for project managers. Be persistent and kind, but don’t stop poking until you get the truth.
  5. Executive Whisperer – Anticipating your sponsor’s reactions to project twists and turns is a useful skill. Even more important is understanding the fears that these project situations will awaken in your senior leaders. Understanding those fears helps you identify the information to share to either reassure them or give them clear options to help you address the concern. Executive whispering is best performed going into a project, when you can have a conversation with your sponsor and other stakeholders about the risks they are most concerned about and the positive outcomes they value most. That way, you can whisper to your senior leaders to help you guide the project and control their fears!

Tips for Managing Small Projects

When managing small projects, less is more. A small project needs to be a lean machine, and unnecessary work and inefficiency gum up the works. Here are five tips to make your small projects run more smoothly.

Tip #1: Small projects often have tight budgets and short durations. There’s no room for unnecessary steps or nice-to-have deliverables.

Hash out what the customer really wants (project scope) – and put it in writing. Don’t forget to document what isn’t in scope. Say you’re building a web site for your customer. In a meeting with the customer, you develop the following scope:

Scope

  • Choose web tools, templates, and add-ons based on customer requirements for online sales and contact options.
  • Design, prototype, and build a 3-page website: home page, purchasing page, and contact page.
  • Two rounds of edits during design phase.
  • One round of edits during development.
  • Test website.

Out of scope

  • Design changes after acceptance of design will be handled as change requests. Changes after the first round of development edits will be handled as change requests.
  • Customer purchases web tools, add-ons, and hosting.
  • Customer resources perform review and acceptance testing.

After you nail down scope, be sure to balance the project triple constraints (scope, time, and budget). Are the desired timeframe and budget realistic relative to the project scope? If not, work with the customer to identify an acceptable compromise: maintain scope and increase the time or budget, trim the scope, or some other combination.

Tip #2: Do just enough to make the project a success.

This tip might sound contra-intuitive, but your goal as project manager is to complete the project successfully. That means delivering what the project is supposed to – not to exceed expectations. Make sure your team works on just the work that’s required and don’t address other objectives or nice-to-have deliverables.

Tip #3: Build an effective team and keep it that way.

If you have a choice, use people who know how to do the kind of work the project requires, and ideally who have worked well together in the past. Good teamwork is important. People who work well together might get more done, even if they are a little less experienced.

Make sure your team knows what to do and help clear the way, so they can get their work done.Keep your team members motivated. Help them understand how they contribute to project success and make them feel appreciated.

Tip #4: Keep things simple.

Time, money, and resources can be hard to come by on small projects. Don’t squander them by over-complicating things. Use simple processes and procedures for tracking time, managing changes, communicating, and so on. Ask for only the information you need to manage the project and hold only the meetings that are necessary.

Tip #5: Keep things organized.

You can’t afford to waste time looking for information, performing work that someone else already finished, or redoing work because the instructions weren’t complete or clear.Good organization also helps everyone else find what they need.Store project information where it’s easy to get to by everyone who needs it.

For more tips on managing small projects, check out my updated course, Project Management Foundations: Managing Small Projects.

 

Analyzing Profit and Loss with QuickBooks Classes

QuickBooks classes are ideal when you need to analyze finances across accounts, income, expenses, customers, jobs, vendors. Classes help you track financial results by categories such as business unit, location, partner, or item. Classes can span time and items, too, because you assign a class to individual transactions (such as checks, bills, sales receipts, and invoices) as well as to specific line items on invoices or bills.

Choosing the Right Dependency Between Project Activities

The schedule logic for a project is the collection of dependencies you create between activities. The goal of this schedule logic is to provide a realistic model of when project activities should occur. Want to up your scheduling game? This article explains when to use each dependency type to link activities.

Finish-to-start is the one you’ll use most often. A finish-to-start dependency tells you that when one activity (called the predecessor) finishes, the next activity (the successor) can start. For example, you have to finish writing some code before you can test it. If you don’t work in software, maybe this example will resonate: when your older child teases the younger one, the younger one starts crying.

On the other hand, the start-to-finish dependency type is rare (which is a gift because it’s also confusing). This dependency means that the start of one activity determines when another one finishes. It’s confusing because the predecessor occurs later than the successor, as shown in the figure, and most people think of predecessors occurring before successors. (Remember, with dependencies, the predecessor is the activity that controls the timing of the successor, not when it occurs time-wise.) For example, consider a sales clerk who works a shift in a retail store. To keep the store open for customers, the clerk for the next shift has to show up to start his or her shift before the sales clerk on duty can go home (finish the shift).

Let’s look at the remaining two dependency types: start-to-start and finish-to-finish.

Suppose one person is scheduled to spend 10 days writing software documentation and another one is scheduled to work 10 days reviewing the documentation to make sure it’s accurate and clear. At first glance, you might think start-to-start and finish-to-finish dependencies work equally well. When the writing starts, the review could start almost immediately. Or, when the writing is complete, the review could finish soon after.

But start-to-start dependencies can cause trouble if activities don’t occur as scheduled. Suppose the writer runs into issues with the software and the writing task is going to take 15 days instead of 10. As you can see in the figure, the writing and review started at the same time, which means that the review is scheduled to finish 5 days before the writing. Some of the writing wouldn’t get reviewed unless you caught this error in your schedule logic.

The writing and review activities should be linked with a finish-to-finish dependency. That way, the schedule logic guarantees that the review doesn’t finish until the writing is complete, even if the writing takes longer. This dependency also works if the review takes less time than writing—say, 5 days. With finish-to-finish, you could wait 5 days before starting to review documentation, as shown in the figure below. If the writing takes longer than you expect, the delayed finish date for writing also delays the finish for review.

As you can see, almost all your dependencies will be finish-to-start or finish-to-finish. Another dependency best practice is to avoid negative lag (also called lead), because it implies that you know when the predecessor activity will finish. (You can explore this practice in this movie from my revamped and updated course, Project Management Foundations: Scheduling, which was released in April 2018).

Taming a Crazy To-do List

No matter how carefully I manage my workload, I end up buried with to-dos every so often. If you’re like me, an overwhelming to-do list could make you freeze up and not get anything done. My solution is time-management heresy!

Crossing a to-do off my list gives me a boost of energy and motivation to get more done! So, I do something quick and easy that I want done, even if its priority couldn’t be any lower. With my energy and motivation restored, I can go back to a more orthodox time management approach. My newest course, Project Tips Weekly, releases one short movie each week, so it’s a great example of this tactic—from my perspective as the author as well as for viewers.

Here’s how to tame an overwhelming to-do list:

1.      Pick a task that won’t take much time (5 to 10 minutes max) and that you want to get done. You know which one it is. Maybe it’s cleaning up the receipts on your desk, mapping out your day, or watching a LinkedIn Learning movie!

That’s one thing less to do. If you keep a list of to-dos, you can mark the task as complete and bask in that feeling of accomplishment. That brings up a question…

2.      Do you have a to-do list?

A heap of crumpled, smudged notes with scribbled to-dos doesn’t count.

If you don’t have a list, take 10 minutes and add everything you can think of to it. Include importance, urgency, and level of effort for each entry if you know what they are. (Stop at 10 minutes. You can add to the list any time later on.)

Writing up a list on paper does commit you to your to-dos, and you get satisfaction from drawing a line through each task you complete. However, you’ll rewrite to-dos onto new sheets as priorities change and new to-dos come up. If you throw past lists away, you lose your work history, too.

A spreadsheet, OneNote table, or some other app can help in a lot of ways. You can sort the entries by importance, urgency, or level of effort. You can mark to-dos as complete and move them to your completed list. If you include the date you complete each to-do, you can motivate yourself when you’re feeling down by looking back at everything you’ve accomplished the past, week, month, or year.

3.      Sort the list by importance, then urgency, then level of effort.

With a sorted to-do list, it’s easy to see your important and urgent to-dos.

In the example below, I have one to-do that’s important, urgent, and doesn’t take a lot of time: prepping movies for my Project Tips Weekly course – which has one short tip come out each week. Depending on the tip, I can get one prepped in an hour or two. That’s definitely the first thing I’m going to tackle after the next step.

4.      With the sorted list in front of you, get your important and non-urgent to-dos on your calendar!

Because they aren’t urgent, they’re easy to forget unless you schedule them. Be realistic. Don’t try to finish them all in the next few days. Space them out so you have time for important and more urgent work.

Last year, I made a list of places I would like to visit on vacation. Some friends and I agreed those were places to go and that’s how it sat for almost a year. Finally, I realized I needed to get at least a few on the schedule, so I typed in 2018, 2019, 2020 into OneNote and then moved my top-priority vacation spots into one of those years. Lo and behold, four of those are now on my calendar!

LinkedIn Learning videos might fall into this category. Suppose you want to learn a topic, whether it’s Microsoft Project, gathering requirements, or fixing your photos with Photoshop. You can schedule 10 or 15 minutes every day or two to watch a few movies on that topic. Before you know it, you’ve finished an entire course!

5.      Now, grab one of your important/urgent to-dos and get to work!

By the end of the day, you may have finished several things on your to-do list, including a couple of important, urgent tasks. Move those to-dos into a Completed list and enjoy another energy boost seeing how much you’ve accomplished.

I’m enjoying working on my Project tips course. Instead of prepping several dozen movies in a short time, I can add individual movies to my to-do list – one each week for the next calendar quarter.

6.      Before you call it a day, take 5 to 10 minutes to plan what you will tackle from your list tomorrow.

It might take a week to get the to-do list under control. However, it takes only a few minutes each day to keep your list under control. For more on time management, check out Chris Croft’s course.

Saving Customized Views in Project

Saving custom views is easy when you plan ahead. Modifying a built-in view and then saving it as a custom view is still easy, but it does take a few more steps.

If you set out to save a customized view to use again and again, the steps are easy:

1. Display the built-in view that’s closest to what you want, like the Detail Gantt view.

2. On the Task tab or View tab, click the bottom half of the Gantt Chart button, and then choose Save View.

3. In the Save View dialog box, name the view, for instance, C_Updating, and then click OK.

I like to add C_ at the beginning of each custom view, so they’re easy to spot in drop-down lists and in the global template.
Project creates the new view and a new table (C_Updating Table1) to go with it.

4. Now you can customize the view and table however you want.

The custom view is available to use in the future – and the original built-in view is still available.

What if you display a built-in Project view and go wild building a super-cool customized view with filters, groups, timescale settings, table columns, and formatting? THEN you realize you want your creation to be a custom view and you want the original built-in views definition back. No biggie. A few more steps get you where you want to be.

Suppose you want a view for updating tasks. You’ve displayed the built-in Tracking Gantt view, applied the In Progress Tasks filter, set the timescale to days, and added and rearranged columns in the table. Remember, when you modify a built-in view, Project saves copies of the modified view and table in your Project file (using the built-in view and table names). The global template still contains the original built-in definition of the view and table.

Here’s what you do to save the modified view as a new one and bring back the original built-in view:

1. On the View tab, click the bottom half of the Gantt Chart button (or any other view button like Task Usage or Resource Usage), and then choose Save View.

2. In the Save View dialog box, name the view, like C_TaskUpdating, and then click OK.

Just like saving a view before you add all the modifications, Project saves the new view and a new table, in this example, C_TaskUpdating for the view and C_TaskUpdating Table 1 for the table. If you have the “Automatically add new views, tables, filters, and groups to the global” option turned on (it’s in the Project Options dialog box Advanced category), Project also saves the new view and table to your global template.

3. To get the built-in view (Tracking Gantt in this example) back to its original definition, click the bottom half of the Gantt Chart button (or the appropriate view button on the View tab) and choose the built-in view.

4. Click the bottom half of the Gantt Chart button (or other view button) again. This time, on the drop-down menu, choose Reset to Default.

5. When the message appears telling you that you are about to revert to the view from your global template, click Yes.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Now, you have your new view with all its customization, and your built-in view is back to the original definition.

On another note, what if other team members need access to your project along with your custom view handiwork but don’t have Microsoft Project? You might want to check out Microsoft Project Viewer.

 

 

Outlook Rules Rule

Microsoft Office rules can take the drudgery out of managing emails. Say you get a gazillion emails from the treasurer of the board you belong to and you want all those emails to go into a separate folder. A rule can automatically move emails from that email into the folder you specify. Even better, suppose you get emails from someone you’d rather not hear from. You can set up a rule to delete those emails straight away.

Once you’re spoiled by Outlook rules, you won’t want to work without them. If you get a new computer or use Outlook on a desktop and laptop computer, you can move your rules from one computer to another.

Let’s take a quick look at how to create a rule in Outlook 2013.

  1. In Outlook, you can select an email to grab its email address to start your rule. If you aren’t going to use an email address, skip this step.
  2. On the Home tab, in the Move section, choose Rules, and then choose Create Rule.
  3. In the Create Rule dialog box, turn on the checkboxes for the conditions you want to use. For example, if you selected an email, turn on the From [email address] checkbox. You can also turn on the “Subject contains” checkbox and type the words you want, such as “to-dos.”
  4. In the Do the following section, tell the rule what you want Outlook to do with the incoming email. For example, turn on the “Move the item to folder” checkbox, and then select the folder you want, such as To-Dos or Deleted Items (if you want it gone). If you don’t have a folder yet, in the Rules and Alerts dialog box, click New and create the folder.
  5. Click OK. At this point, a Success message box appears. To apply the rule to all existing messages, turn on the checkbox whose label starts with “run this rule now” and click OK.

Now let’s get rules over to another computer:

  1. On the Home tab, in the Move section, choose Rules, and then choose Manage Rules & Alerts.
  2. On the E-mail Rules tab, click Options (just above the Rule table).
  3. Click Export Rules.
  4. Select the folder where you want to save the rules file. In the File name box, type a name for the file.
  5. Click Save. The rules export file has an .rwz extension.

rules

To import the rules on another computer:

  1. Copy the rules export file to that computer or make sure it’s available on the network.
  2. Open the Manage Rules & Alerts dialog box on that computer, click Options, and then click Import Rules.
  3. Select the rules export file.
  4. Click Open.

Ta-da! You’re rules are available in Outlook on this computer.

Type Faster with AutoCorrect

Does your brain produce words faster than your fingers can type? Are you tired of correcting your fat-fingered typos? Microsoft Office AutoCorrect not only fixes typing mistakes. You can take the tedium out of typing by building shortcuts for long words of phrases into AutoCorrect.

Out of the box, AutoCorrect has fixes that change misspellings like abotu into about, or replaces “:)” with a happy face. If you consistently mistype words, you can add the typo and the correct entry to AutoCorrect. That way, AutoCorrect automatically fixes it next time around. A couple of my consistent typos are cateogry and accoutn.

Why not use AutoCorrect to speed up your typing, too? When I’m working on a QuickBooks book, I use phrases like dialog box, dialog boxes, financial institution, and “On the Home Page, click Create Invoices” a gazillion times. But I don’t have to type them out every time. I create AutoCorrect entries for phrases like those, and let it do the heavy lifting. When I type dbx, AutoCorrect changes it to dialog box. Dbxs turns into dialog boxes. Finin expands to financial institution. And hpci bursts out into On the Home Page, click Create Invoices.

By the way (AutoCorrect shortcut btw), when you set up AutoCorrect entries, they work in Word, Excel, Outlook, and so on. Try it. I think you’ll like it.

Here’s how to create AutoCorrect entries:

  1. On the File menu, choose Options, and then choose Proofing.
  2. In the Word Options dialog box, click the AutoCorrect Options button.
  3. In the AutoCorrrect dialog box, type your shortcut in the Replace box.
  4. Type the expanded phrase in the With box.
  5. Add additional entries it you want.
  6. When you’re done adding entries, click OK to close the AutoCorrect dialog box.

AutoCorrect

AutoCorrect entries

That’s it! The only downside is when you work on someone else’s computer and dbx stubbornly refuses to expand.

If you get a new computer, it won’t have all your AutoCorrect entries. No problem! You can copy a file with your AutoCorrect entries to another computer. The hard part is knowing where to look for the AutoCorrect file.

It’s in C:\Users\<your user name>\AppData\Roaming\Microsoft\Office. The file you want for English is MSO1033.acl. All you have to do is copy that file onto a thumb drive, plug the drive into the other computer, and copy it into the same folder on the other computer. (If you’re copying to a brand new computer, overwriting the file is perfectly OK. If you overwrite a file that already has custom AutoCorrect entries, those entries are gone.)